For the past three years our awesome Field Crew has been hard at work, upgrading the Elm Avenue pipeline. The purpose of this project is to remove the old 14” steel line between Main Avenue and Filbert Avenue, and replace it with a brand new water line.

Project History

  • 2013 Phase 1: Section between Main Avenue and Walnut Avenue completed
  • 2014 Phase 2: Section between Walnut Avenue and Chestnut Avenue completed
  • 2015 Phase 3: Section between Chestnut Avenue and Filbert Avenue (Will be completed soon)